Robinson Street 230 kV Underground Transmission Line
At OUC, we’re committed to providing safe, reliable and affordable service. A major part of making this goal a
success is a strong transmission system. Sometimes it requires new construction or upgrades to our existing
infrastructure. We realize the inconvenience construction may have and will do everything possible to complete
our work quickly and safely.
Project Overview
To provide the most dependable service possible and meet growth demands in Central Florida, OUC The
—Reliable One is installing a new underground electric transmission line along Robinson Street from
North Fern Creek Avenue to North Crystal Lake Drive/Maguire Boulevard. This work includes excavation to install an
underground duct bank stretching 0.96 miles. No existing overhead lines will be removed or relocated.
OUC is working in coordination with the Florida Department of Transportation's (FDOT) Robinson Street Resurfacing, Restoration and
Rehabilitation (RRR) project from Mills Avenue to Maguire Boulevard/Crystal Lake Drive and the City of Orlando's Robinson Street Sanitary Sewer Improvements project. OUC's 230 kV
transmission project will be completed ahead of FDOT's RRR project.
Together, these projects will transform Robinson Street. Below, courtesy of FDOT, are streetscape renderings of the
future Robinson Street after all roadway, streetscape, and utilities improvements are completed.
For more information on the FDOT resurfacing project, click here
For more information on the City of Orlando project, click here.
More information about OUC's project is below:
OUC Project 230 kV Underground Transmission Project Location Map
Project Schedule and Traffic Impacts
Construction began April 8, 2024, and will run along portions of Robinson Street. The full project's anticipated
completion date is January 2025. We appreciate your patience and understanding as we work to make enhancements to
ensure electric reliability for our growing community.
Most of the transmission project work will be done during normal working hours, Mondays through Saturdays.
Multiple crews will work on different sections of the road at any given time. Signage will vary according to the type
of work activity.
Below is the anticipated work schedule through May 27, 2024.
*Please note: This schedule is subject to change and will be updated as needed.
Work Crew Locations
Traffic Impacts
Dates: Friday, 5/10/2024 - Tuesday, 5/21/2024
Times: 24-hours a day
North Bumby Avenue to North Glenwood Avenue
East Robinson Street will be reduced to one lane in each direction from North Hillside Avenue to east of North Bumby Avenue. Please expect delays.
Dates: Monday, 5/20/2024 - Monday, 5/27/2024
Times: 24-hours a day
North Graham Avenue to North Primrose Drive
East Robinson Street will be reduced to one eastbound travel lane. Please expect delays.
Westbound lanes of East Robinson Street from North Primrose Drive to North Graham Avenue will be closed completely. Please follow the detour signs to East Livingston Street.
Dates: Friday, 5/10/2024 - Monday, 5/27/2024
Times: 24-hours a day
North Fern Creek Avenue to Hampton Avenue
East Robinson Street will be reduced to one westbound travel lane. Please expect delays.
Eastbound lanes of East Robinson Street will be open to local traffic only
from North Fern Creek Avenue to Rosearden Drive. Local eastbound traffic will be able to turn right onto Rosearden Drive
to travel south.
Eastbound lanes of East Robinson Street will be closed from Rosearden Drive
to Hampton Avenue.
Businesses and sidewalks will remain open.