|
Frequently Asked Questions
Orlando Utilities Commission
(OUC) and Southern Company, along with the U.S. Department of Energy (DOE), are
building an advanced coal-fired electric power plant at the Curtis H. Stanton
Energy Center. This new generation technology is unique because of its efficiency, cost
effectiveness and environmentally superior use of certain types of coal that
make up half the world's proven reserves. This project will help ensure that
these abundant coal reserves can provide the clean, affordable energy that is
needed to build a better, cleaner future.
Following is information about the project and its technology.
WHAT IS IT?
The project will demonstrate advanced power generation systems
using Integrated Gasification Combined Cycle (IGCC) technology by constructing
new facilities at the existing Stanton Energy Center. The facilities will
convert coal into synthesis gas for generating electricity while substantially
reducing emissions of sulfur dioxide, oxides of nitrogen, and mercury, as
compared to conventional coal-fired power plants.
IGCC technology uses synthesis gas
derived from coal to drive a gas combustion turbine and hot exhaust
gas from the gas turbine to generate steam from water to drive a steam
turbine; both turbines generate electricity. At full capacity, the new
coal gasifier will use about 137 tons of coal per hour to produce
synthesis gas. Combined, the two turbines will generate about 285 MW
(megawatts) (net) of electricity. This combined-cycle approach of
using a gas turbine and steam turbine in tandem increases the amount
of electricity that can be generated from a given amount of coal.
WHERE WOULD IT BE LOCATED?
The project will be located at Orlando Utilities Commission
(OUC's) existing Stanton Energy Center near Orlando, Florida, which currently
generates electricity using two coal-fired units, each rated at about
465 MW, and a natural gas-fired combined-cycle unit rated at about 633
MW. The Stanton Energy Center is about 13 miles east-southeast
of Orlando’s downtown area. The project will be constructed on
about 35 of the 1,100 acres of land that were previously cleared,
leveled and licensed for power plant use. The project equipment will be
located between the existing coal-fired units and the existing natural gas-fired
combined-cycle unit.
WHO IS INVOLVED?
The project is proposed by Southern Company in partnership with OUC, whose
Stanton Energy Center will host the project. Another team member is KBR, the company responsible
for engineering and procurement of the gasification equipment. The U.S.
Department of Energy (DOE) also is involved because the gasifier portion of the
project has been selected for cost-shared funding by DOE under the Clean Coal
Power Initiative (CCPI) program.
WHAT IS ITS PURPOSE?
To operationally demonstrate the gasifier systems within the IGCC technology
at a sufficient size to prove that the technology is efficient, economical,
reliable and environmentally acceptable such that utilities throughout the
United States would seriously consider constructing and operating similar
facilities commercially.
To provide reliable and economical power service
to OUC’s existing and future customers.
WHEN WOULD IT BE BUILT AND OPERATED?
Construction will begin in 2007; operation of the combined cycle unit is
planned for late 2009; and operation of the Orlando Gasification Project is
planned for mid-2010. After the demonstration project is completed, it is
expected the facility will continue in long-term operation.
HOW MUCH WOULD IT COST?
The gasification project is valued at $844 million,
including permitting, design, construction, startup and 4 1/2 years of
operation, maintenance and evaluation expense. The DOE will contribute $294
million with the remaining $550 million being contributed by OUC and Southern
Company.
WHAT NEW EQUIPMENT WOULD BE REQUIRED?
New equipment for the project will include a gasifier, gas and
steam turbines, a 205-foot stack, mechanical draft cooling towers, synthesis gas
cleanup facilities and particulate filtration systems. Wherever possible,
existing facilities and infrastructure located at the Stanton Energy Center
will be used. These include plant roads, administration buildings, coal
delivery and handling facilities, water and wastewater treatment systems, and
solid waste disposal facilities. A new 3,500-ft onsite transmission line will
be constructed from the IGCC to the existing onsite substation to serve as an
electrical interconnection.
WHAT ARE THE ENVIRONMENTAL PERFORMANCE GOALS?
The project is expected to remove up to 95 percent of the sulfur dioxide produced
in the IGCC process using coal that contains up to 0.4 percent sulfur. The removal of
nearly all of the fuel-bound nitrogen from the synthesis gas prior to combustion
in the gas turbine will result in appreciably lower oxides of nitrogen
emissions compared to conventional coal-fired power plants. Over 90 percent of mercury
and more than 99.9 percent of particulate emissions will be removed. About 25
percent
less carbon dioxide will be produced compared to typical emission rates at
conventional coal-fired power plants. The project will discharge no
liquid effluent from the site. Ash generated by the gasifier will be combusted
in the existing coal-fired units, marketed for use as activated carbon or
trucked to the existing onsite landfill for permitted disposal. |